HK Offshore LNG Terminal Project Post-Trenching Services for LPS Pipeline

TIME:2024-02-20 16:27:00 浏览次数:36次

Place: Hong Kong

Work Period: 2021

brief introducfion

Hong Kong Offshore LNG Terminal Project involves the construction of an offshore LNG receiving facility, which shall include the post trenching works for LPS pipeline, with an 18km subsea gas pipeline of 20 inch, connecting from the Gas Receiving Station to Lamma Power Station. This 20 inch LPS pipeline starts from KP0 at FSRU Jetty, turn to northeast and be connected to the pre-laid LPS pipe. It shall be buried at a depth of more than 3.6m by means of a jetting machine. GOW is responsible for site monitor and supervision, providing working vessels, environmental-protection frame and silt curtains, engineering personnel and diving support, facilitating the post-trenching operation etc.